A vending machine acceptance retest record should preserve the original failure. Replacing “fail” with “pass” loses the information needed to judge whether the correction addressed the cause.
Vending failed test corrective action should identify the adjustment, component or software revision and the person authorizing it. A changed package or reduced loading capacity can alter the agreed scope and may require buyer approval under the order's change process.
Retest the original failed scenario and check nearby functions that the correction could affect. A successful empty-cabinet test does not close a failure that occurred under a full load. Keep the setup and outcomes together.
Vending test result version history should show the final accepted configuration and any remaining limitations. Use the configuration revision record to connect the test evidence to the delivered machine.